Elizabethtown Gas is upgrading natural gas infrastructure in Perth Amboy, affecting the following streets: Alpine Street, Amboy Avenue, Boggs Street, Chester Street, Francis Street, Grove Street, Keene Street, Myrtle Street, and Spring Street. 
 

Current update – week of 2/17/26

Work was delayed due to weather and site conditions. The contractor plans to return on 2/17/26 to complete the remaining service renewals and retire the main.

Inclement weather could alter schedule.

Project updates (Elizabethtown Gas / PSE&G)
For the most current schedule and street-by-street updates, visit:
View project updates

Previous phases (for reference):

Main installation – 11/6/24-12/5/24

Service renewals – 1/2/25 – 3/7/25

Main retirement – 3/10/25-3/17/25

Once all work is completed – 90 day settlement period and project will be paved.


This project includes replacing aging gas mains with durable plastic pipe and relocating gas meters from inside homes and businesses to the outside for enhanced safety and reliability.
We appreciate your patience and understanding as we work to improve your neighborhood. For the most current updates, visit www.elizabethtowngas.com/neighborhood
Proyecto de Reemplazo de Tuberías en Perth Amboy
Elizabethtown Gas está mejorando la infraestructura de gas natural en Perth Amboy, afectando las siguientes calles: Alpine Street, Amboy Avenue, Boggs Street, Chester Street, Francis Street, Grove Street, Keene Street, Myrtle Street y Spring Street. 
 
Actualización actual – semana del 2/17/26
El trabajo se retrasó debido al clima y las condiciones del sitio. El contratista planea regresar el 2/17/26 para completar las renovaciones de servicio restantes y retirar la tubería principal.
El clima severo puede cambiar el cronograma.
Actualizaciones del proyecto (Elizabethtown Gas / PSE&G)
Para ver el cronograma más reciente y actualizaciones por calle, visite:
Ver actualizaciones del proyecto

Fases anteriores (para referencia):
Main installation – 11/6/24-12/5/24
Service renewals – 1/2/25 – 3/7/25
Main retirement – 3/10/25-3/17/25
Una vez que todo el trabajo esté completado, habrá un período de liquidación de 90 días y el proyecto será pavimentado.